Wednesday, 20 February 2013
Tuesday, 19 February 2013
Thursday, 7 February 2013
08.02.13
B01 - Boiler North Chipping of Foundation start
B01 - Boiler Foundation F11 Extraction of Sheet Pile
B01 - Boiler FD Fan preparation for rebar concrete cap
B02 - Chimney Excavation
L05 - Absorber preparation f or Excavation
L13 - Aeration Basin Spun Piling
B63 - Turbine Hall Sheet pile strutting
Panoramic View of Intake Area - looking South East
B06 - Bunker/Mills Erection Preparation works (Survey)
Panoramic View of Intake Area - looking North West
Panoramic View of Switchyard
F01 - Switchyard Jack-in piling
Wednesday, 6 February 2013
06.03.13
L13 - Aeration Basin Spun Piling
F01 - Switchyard Jack-in piling
C04 - Coal Yard PVD Installation
E02 - CW Intake Pump house Sheet pile deliveries
B01 - Boiler PA Fan Foundation
C04 - Coal Yard area
B01 - Boiler Foundation F1 Pedestal
Tuesday, 5 February 2013
05.02.13
B63 - Turbine Hall Sheet pile strutting
E50 - CW Pipe Spun Piling
B63 - Turbine Hall Sheet piling
B01 - Boiler Foundation F11 Sheet pile removal
B01 - Boiler Foundation F10 Lean Concrete
B01 - Boiler Foundation F1 Pedestal
B06 - Bunker Bay Beam Slab shuttering
F01 - Switchyard Piling
E02 - CW Intake Sheet pile delivery
C04 - Coal Yard PVD Installation
04.02.13
E05 - CW Pipe Piling
B06 - Bunker / Mills Erection preparation works
B63 - Turbine Hall foundation sheet piling
B01 - Boiler North part backfilling
B01 - Boiler Cavity area & South Part Foundation works
B01 - Boiler Foundation pedestal F3
B01 - Boiler North part Backfilling (gravel)
L13 - Aeration Basin Spun Piling
B02 - Chimney Excavation