Sunday, 3 February 2013

02.02.13

L13 - Aeration Basin Piling

B06 - Stripping of Forms for Mill #1

B01 - Boiler Foundation Pedestal F11

B01 - Boiler Foundation Excavation/Hacking of Piles F10

B01 - Boiler F3 South and F6 Rebar/Forms/Scaff for Pedestals

B06 - Bunker Bay remaining Beam Slab at Section 3  

E50 - CW Discharge Spun Piling

B63 - Turbine Hall Sheet Pile Strutting


B63 - Turbine Hall Excavation for MBFP foundation
C04 - Panoramic View of Coal Yard

C04 - PVD Installation at Coal Yard

F01 - Switchyard Spun piles