B01. Boiler steel structure and Duct erection
General veiw From East
B06. Bunker Bay area Steel Structure Tier #4
erection, Cool Air duct & Silo Cone erection
View from East
B01. Boiler steel structure &
Hot air duct erection
View from North
Hot & Cool Air Duct and Silo Cone erection
view from South
Bunker bay area Steel structure,
Grating & Silo cone erection
B02. Chimney - concrete pouring on
Windshield slide
Started on 18-Oct-13
B68. Transformer building -
side wall concrete in progress
B33. Unit Electrical building,
First roof slab concrete work
B35. Boiler Electrical building,
ground floor roof slab work
B35. Boiler Electrical building -
Auxiliary Transformer foundation
on 22-Oct-13
B35. Boiler Electrical building -
Auxiliary Transformer foundation - back filling
on 24-Oct-13
B63. Turbine Hall Civil work
C05. Crusher house foundation - Rebar installation
C07. TT23. Transfer Tower foundation
rebar installation
C40. Light fuel oil storage foundation
L13. Aeration Basin area -Sheet piling
C71. Electrical building near Crusher House
D01. Ash Storage - pile cap preparation
F01. Switchyard Ganty erection
L05. Absorber shell foundation, rebar installation
L10. Booster Fan Pedestal - steel rebar installation