Monday, 28 October 2013

28.10.13

B01. Steel structure & Duct erection
General view from West

B06. Bunker area steel structure and Silo erection
General view from East
                                                
                                              B01. Steel structure & Hot air Duct erection
                                                view from North

B01. Steel structure Tier 3 & 4 erection,
Hot Air duct erection, B06. Bunker bay steel erection
Tier 3 & 4 and Silo Cone erection,
general view from South
                                                              Grating erection


                                            B02. Chimeny erection, Windshield slide
                                                     concrete pouring in progress
                      
                                             B33. Unit Electrical building,
                                                     concrete rebar installation


                                           B33. Unit electrical building first floor
                                                    roof Slab concreting,

                                           B35. Boiler Electrical building roof slab concreting
                                           
                                           B35. Boiler electrical building - Auxiliary
                                                    transformer foundation/Pedestal work
                         
                                            B63. Turbain Hall civil work

                                            B63. Turbin Hall - excavation  


B68. Transformer Building
side wall concreting work
                                            B68. Transformer building concreting work,
                                                      view from South
                                            C07 TT23 - Transfer Tower foundation
                                                                 concrete reforming work
                                           C71. Electrical building near Crusher house,
                                                      piller rebar installation
                                           C05. Crusher house foundation work
                                           
                                          G06. Water production plant foundation work


                                         B07. Fabric Filter pile replacement
                                                  work in progress
                                             L05. Absorber foundation - back filling
                                             L13. Aeration basin area sheet file installation
                                             L10. Booster Fan pedestal concrete reform work