Power Block General view from East
B33. Unit Electrical Building first floor roof slab concreting
B68. Transformer/ Auxiliary Transformer building
B63. Turbine Hall civil work,
B01/B06 Steel structure Tier 3 & 4 erection
Boiler Hot & Cool Air duct erection
B06. Bunker bay steel structure and
Silo cone erection & grating
Power block East side area, G05/06 Water
treatment plan, and Tank foundation,
view from East
E05. Cooling water piping sleeper,
(Some Pipe delivered at site)
F01. Switch yard Gantry erection,
Trench & Foundation in progress
Power Block general view from West
B01. Steel strcuture Tier #3 & 4 erection in progress
Hot & Cool Air Duct erection in progress,
B06. Bunkery bay area steel structure and
Cool air duct, silo cone erection in progress,
B35. Ground floor slab concrete work
B10 ID fans foundation. B02 Chimney
windshield concrete work, L05 Absorber
Shell, B17 flue gas duct erection
L10. Booster Fan pedestal installation
C05. Crusher house foundation
Coal Handling Transtower Steel structure erection
E02. Cooling water Pump Station
General view
C04. Coal Yard & Stack reclaimer erec