Monday, 19 May 2014

02 May 2014 - Construction Progress Picture



   
B01 - Boiler North View
   
B01 - Pressure Part Erection Ongoing

  


B63 - Steam Turbine Building Civil Work Ongoing





G08 - Compressed Air Production Foundation and Column Work Ongoing


B33 - Unit Electrical Building East View


G25 - Indstrial Water Pumps Station Steel Erection Ongoing


G07 - Demineralised Water Tank, Bottom Plate Installation Ongoing


G02 - Raw Water Storage Asphalt Repair Completed

B68 - Transformer Gravelling Removing and Rail Installation Ongoing


F06 - HV Cable, Civil Work Ongoing




E05 - Main Cooling Water Piping, Sleeper Work Ongoing


B68 - Aux Transformer, Civil work Ongoing


B63 - Steam Turbine Building, Civil Work Ongoing


B63 - Steam Turbine Building, Civil Work Ongoing

B01 - Boiler, Cavity and Tier Steel Beam Installation Ongoing

D01 - Fly Ash Storage

C05 - Coal Crusher House Civil Work Ongoing

B17 - Flue Gas Ducts Erection Ongoing


B07 -  Fabric Filter, Casing Erection Ongoing


B35 - Boiler Electrical building, Cable Tray Installation Ongoing
  

L05 - FGD Absorber Concrete Work Ongoing


L13 - FGD Aeration Bassin


L13 - Aeration Bassin



L13 - Aeration Bassin


L13 - Aeration Bassin


B63 -  Steam Turbine Building, South View


B33 - Unit Electrical Building


E50 - Main Cooling Water Culverts ST. Hall to Aeration Bassin


C30 - Fuel Oil Unloading Area


G17 - Auxiliary Boiler, Rebar and RC work Ongoing


ADV Module Assembly


C30 - Fuel Oil Unloading Area



G17 - Auxiliary Boiler


 
G05 - Water Treatment Plant, Mechanical and Piping Installation Ongoing

B64 - ST Foundation and Generator Foundation Block, Civil Ongoing


No comments:

Post a Comment

Note: only a member of this blog may post a comment.