Power Block as of 21-10-2014
|
B63. Turbine hall - condenser moduel positioning |
|
B63. Turbine hall - condenser module positioning,
view from North |
|
Condenser module at site (second one) |
|
B01. Boiler area general view from North
(Entrance of site) |
|
B01. Boiler Hot & Cool air duct erection, view from North |
|
B01. Boiler Air preheater erection |
|
B33. Unit electrical building 1st floor - Cable pulling on Panel |
|
B06. Bunker bay area pulveriser erection |
|
B06. Fabric filter casing erection |
|
B33. Unit electrical building - ground floor, MV cable pulling |
|
B33. Unit electrical building 1st floor - cable pulling to panel |
|
B33. Unit electrical building - control room, civil work |
|
B33. Unit electrical building roof area - HVAC work |
|
B63. Turbine hall North side, polish plant equipment erection
and steel structure erection |
|
B63. Mail cooling water out let pipe & valve erection |
|
B63. Turbine hall - large bore pipe erection |
|
B63. Turbine hall, general view from North |
|
B63. Turbine hall - Steel structure and Mechanical erection
veiw from North |
|
B63. Turbine hall steel structure erection, view from North |
|
B63. Turbine hall - general view from East |
|
B68. Auxiliary transformer erection |
|
B68. Main transformer erection |
|
C03/30 - Fuel oil pump station & unloading area, steel structure
erection, C40. Fuel oil storage tank erection |
|
C72. Electrical building - ground floor |
|
H03. Pipe rack erection
G08. Air compresser building, equipment erection |
|
G17. Auxiliary boiler erection |
|
G25. Water pump station, equipment and cable tray erection
G02. Raw water supply storage tank erection |
|
G16. Waste water treatment plant
L13. Aeration tank erection |
|
E05. Under ground cooling water piping saddle foundation work |
|
G05. demin plant equipment erection, streel structure erection
G07 & G20. Demin stroage tank erection |
|
B01. Boiler erection |