Tuesday, 25 November 2014

24.11.2014 - Power Block area


Plant general view from East

B01. Boiler erection - bottom aarea

B01. Boiler erection general view from South

B10. ID fan erection

B10. & B07. Fabric filter casing and I D Casing assembly


B33. Unit electrical building panel and cable pulling

B33. Cable termination

B33. Cable termination

B33. Cable termination

B33. Unit electric building area ,HO3 cable rack erectoin

B33. Control room




B33. Unit electrical building roof area - HVAC  work

B35. Boiler electrical building general view

B63. Turbine hall area - Polish plant equipment erection

B63. Turbine hall area general view from North

B63. Condenser module on position

B63.Turbine hall sid view

B63. Turbine hall - heaters and large bore pipe erection

B63. Turbine hall - feedwater tank erection

B68. Main transformer erection

B68. IPB erection

B68. Turbine hall area IPB erection

C30.Fuel oil unloading area

E05. Cooling water under ground piping foundation

H01. Sleeper way foundation

E50. Outfall foundation Trbine hall to Aration Basin


F06. Hv Cablepulling -(cable bridge)

G05. Demin plant - equipment erection

G17. Auxiliary boiler erecction

G25. Water pump station



L05. FGD Absorber

B33. Electrical buidling area Pipe rack erection

B!&. Flue gas duct erection

L13. Aeration basin civil work

L41. Absorber supply and discharge pipe erection

No comments:

Post a Comment

Note: only a member of this blog may post a comment.