B06. Bunker Bay South Side,
Back filling after water proof painting
B06. Bunker Bay North Side,
Rebar installation for concrete
B01. Boiler Foundation connection beam -
(strengthning work) Back filling, view from North side
B01. Boiler Foundation connection beam -
(strengthning work) Back filling, view from South side
B01. Boiler Foundation connection beam,
strengthning work steel fixing, view from North Side
B01. Boiler Foundation connection beam,
strengthning work, view from South Side
B01. Boiler FD Fan Foundation concreting,
view from West
B01. Boiler FD Fan Foundation concreting,
view from South
view from East
B33. Electrical Building Ground floor work,
view from South
B63. Turbain Hall - Piling work, view from North
B63. Turbain Hall - Piling work, view from South
B02. Chimney Foundation - back filling
L10. Booster Fan foundation reinforcement work
B68. Transformer - Steel fixing
D01. Ash Storage - Bore piling work
C40. Light Fuel Oil Storage - Piling work