B01 - Boiler foundation strengthning work -
backfilling finishing work, view from South
B01. Boiler Area
720 Ton Crane at site
B01. Boiler Foundation - Backfilling
view from SouthB06. Bunker bay concrete work - view from South
B06. Bunker bay concrete work - vew from South
B01. Boiler foundation area - backfilling
B10. ID fan South - Pile cape preparation
B07. Fabric Filter - Pile cap preparation
B33. Unit Electrical Building - Ground floor work
B33. Boiler Electrical building
Tie bar concrete work
B63. Turbine Hall - Piling work North end
View from West
B63. Turbine Hall - Piling work view from North
B63. Turbine Hall North side piling woork
View from south
B68. Transformer - Concrete
C06 - Cool conveyor between C05 & C07
Concrete
C06 - Cool conveyor between C05 & C07
TT23 - foundation backfill
B02 - Chimney - Erection
E50. Cooling Water Culverts - Piling work
E50. Cooling Water Culverts - Piling work
L05. Absorber - Pile cap preparation
L13. Aeration Basin - Piling work
L24. FGD Duction foundation - Pile cap preparation