Saturday, 16 May 2015

16.05.2015

Boiler view from north
Coal crusher house
Fabric filter
FD/PA fans foundations north side
Cooling water pipes
Cooling water pipes
Cooling water pipes being lifted into position
Cooling water pipes being lifted into position
Cooling water pipes
Cooling water pipes
Cooling water pipes
Cooling water pipes
Cooling water pipes
Cooling water pipes
Cooling water pipes
Shaft alignment in progress
Turbine hall Level +16.0m
Turbine hall Level +16.0m
Turbine hall Level +16.0m
Turbine hall Level +16.0m
Turbine hall Level +16.0m
Lube oil room
Turbine hall Level +16.0m
MCW piping
Turbine hall Level +16.0m
Turbine hall Level +16.0m
Lube oil room
Waste water treatment plant
Waste water treatment plant
Waste water treatment plant
FGD aeration basin
Light fuel oil tank
Condensate make up tank
Boiler acid waste pit
Demin plant
Raw water tanks
Condenser neck prepare for welding
Condenser neck prepare for welding
Waste water treatment plant
Boiler electrical building piperack
FD/PA fans foundations south side
Fabric filter