| Power Plant general view from West |
| Fabric filter area general view from North |
| Boiler area general view from North |
| PA/FD fan eration - North side |
| Under boiler area - conveyor erection |
| Turbine North side - Preparation of Steam blow out |
| Cooling water piping erection - Critical area Section 1D (also below listed) |
| Cooling water piping - backfilling, near Turbine hall |
| Cooling water piping Belt tie |
| Out fall roof concrete work - From Turbine hall to Aeration |
| Outfall roof concrete work - Turbine to Aeration |
| Turbine hall - veiw from South |
| Boiler area general view from South |
| FGD pump station grouting work |
| Aeration basin - GRP Pipe erection |
| GRP Pipe erection |
| Aeration basin GRP Header erection |
| Absober effluent pipe erection |
| FGD pump station |
| Absorber supply and discharge pipe erection |
| FGD area |
| Main cooling water outlet pipe erection |