27.05.2015
Boiler area general view from North |
PA/FA Fan erection work - North side |
Fabric filter area general view from North |
Under boiler area - Scrap conveyor erection |
Scrap conveyor area - civil work |
Main cooling water out let area |
Main cooling water piping area (No manpower working) |
Cooling water piping - Critical area Section 1D |
Piping - Section 1 D area (piping welding) |
Ssection 1 D area |
Section 1D area |
Section 1D area |
Section 1D area |
Section 1D area |
Piping Back filling - Near Turbine hall |
Cooling water piping - Tie belt |
Outfall roof concrete work - From Turbine hall |
Outfall concrete work - From Turbine to Aeration |
Waste water treatment area - pump installation |
Aeration - Effluent piping and Civil concrete wall |
Aeration station Header positioning |
FGD pump station - civil concrete wall |
Aeration basine GRP piping erection |
Aeration station |
PA/FA fan erection - South side |