Friday, 6 September 2013

05.09.2013


B01. Boiler steel structure erection,
view from North


B01. Boiler steel structure erection,
view from South


B01. Boiler steel structure erection,
view from West

B06. Bunker Bay area steel structure erection,
view from North


B06. Bunker Bay area steel structure erection,
view from South


B02. Chimney Slip form ring erection


B07. Fabric Filter area


B10. ID Fans South foundation rebar work


L10. Booster Fans foundation concreting,
view from South


B17. Boiler Flue Gas Duct foundation backfilling


B33. Unit Electrical Building ground floor civil work



B35. Boiler Electrical Building foundation
rebar work


B63. Turbine Hall civil work





B68. Transformer area foundation civil work


C05. Coal Crusher House pile cap preparation


C07. TT23 Transfer Tower foundation work


C71. Coal Crusher House Electrical Substation
foundation work


E02. Main Cooling Water Intake civil work




L05. FGD Absorber pile cap preparation


L13. Aeration Basin piling completion


L24. FGD Duct pile cap preparation