B01. Boiler steel structure erection,
view from Southeast


B01. Boiler steel structure erection,
view from East


B01. Boiler steel structure erection,
view from North


 B06. Bunker Bay steel structure erection,
view from South


B02. Chimney Slipform ring erection 


B07. Fabric Filter foundation dewatering


B10. ID Fans foundation concreting completed


B17. Flue Gas Duct foundation lean concreting 


B33. Unit Electrical Building foundation,
1st floor column rebar fixing 



B35. Boiler Electrical Building foundation,
column concreting completed 


B63. Turbine Hall civil work 





B68. Transformer foundation firewall rebar fixing,
view from Southwest 


B68. Transformer foundation firewall rebar fixing,
view from Northeast 


C05. Coal Crusher House pile plug preparation 


C06. Coal Belt Conveyors foundation excavation 


C07. TT17 Transfer Tower foundation rebar fixing 


C40. Light Fuel Oil Storage pile cutting 


E02. Main Cooling Water Intake civil work 





G06. Demin Water Effluents foundation brickwork 


L05. FGD Absorber foundation rebar fixing 


L10. Booster Fans foundation soil compacting 


L24. FGD Duct pile cutting 