Thursday, 6 February 2014

05.02.2014 (G05 equipment erection start on 05-02-14)



G05. Demineralized water production equipment
erection started on 05-02-2014

B01. Boiler pressure parts item lifting

B01. Boiler steel structure and
B07. Fabric filter steel structure erection

B01. Pressure parts erection

B01. Pressure parts assembly at site

B01. Boiler steel structure & duct erection
view from South

B01. Piping erection

B01. Steel structure &
B07 Steel structure erection general view

B06. Bunker Bay area steel structure
and silo duct erection

B06. Bunker bay area

B07. Fabric filter steel preassembly area

B07. Fabric filter casing assembly

B07. Steel structure erection

G17. Auxiliary boiler foundation work

B33. Unit electrical building
3rd floor slab concreting


B33. Unit electrical building ground floor,
electrical work

B33. Unit electrical building 1st floor,
plastering work

B35. Boiler electrical building,
3rd floor column erection


B63. Turbine hall basement concrete slab

B63, Turbine hall - South end rebar installation

B63. Turbine hall basement concrete,
view from North




C40. Light fuel oil retention work

C71. Electrical building near crusher house

C72. Electrical building near bunker bay

D01. Ash Storage foundation work

F06. Cable way foundation