B01. Boiler steel structure, Temporary lift installation, view from North |
B01. Boiler pressure parts assembly at site |
B01. Boiler Steel structure, Duct, pressure parts erection |
B01. Boiler steel structure, pressure parts erection, B07. Fabric filter Steel structure erection , view from West |
Pipng material at site for erection |
B06. Bunker bay area, Mill area civil work in progress |
B07. Fabric Filter area steel structure erection, ID Fan foundation |
B33. Unit Electrical building, 1st floor plastering work |
B33. Unit electrical building, transformer area slab concrete, view from East |
B33. Unit electrical building, view from South |
B63. Turbine hall, South end steel rebar installation |
B63. Turbine hall concrete slab |
B63. Turbine hall South end- Concrete slab |
B63. Turbine hall general view from North |
B68. Auxiliary transformer building side wall rebar installation |
C03. Pile cap preparation |
C30. Fuel oil unloading area |
B68 Main transformer building concrete repair work |
C05. Crusher house area column erection |
C40. Light fuel oil retention work |
C71. Electrical building near crusher house |
1250 Ton Crane Dismanteling |
D01. Ash storage foundation work |
E05. Cooling water piping sleeper foundation |
G05. Equipment erection |
G10. Emergency diesel generator foundation |
G16. Waste water treatment plant pile cap preparation |
G25. Operational Industrial water pump station foundation |
B35. Boiler electrical building plastering work |
B35. Boiler electrical building Ground floor |
B07. Fabricl filter hopper and casing assembly |
L05 Absorber shell side wall rebar installation |
L13. Aeration basine foundation work |