B07. Fabric Filter Hopper - erection started on 24 Feb 2014 |
B01. Boiler steel structure, Pressure Parts & duct erection, View from South |
B01. Boiler Pressure parts erection. B07. Steel structure erection & Hopper installation |
B01. Piping erection |
B06. Bunker bay area Mill foundation |
B07. Fabric Filter Casing assembly |
B07. Fabric Filter steel structure & Hopper erection |
B07. Fabric filter casing assembly (Flue gas foundation area) |
B07. Fabric filter steel structure - view from South |
B33. Unit Electrical building, view from South |
B33. Unit electrical building Transformer area, view from East |
B33. Unit electrical building ground floor HVAC erection |
B33. Unit electrical building gound floor exhaust Fan installation |
B33. Unit electrical building ground floor HVAC duct frame installation |
B35. Boiler electrical building |
B35. Boiler Electrical building ground floor, plastering, painting & HVAC erection work |
B35. Boiler electrical building 1st floor - plastering, painting & HVAC erection work |
B63. Turbine hall - general view from North |
B63. Turbine hall General view from North |
B68. Auxiliary Transformer building area side wall rebar installation |
B68. Main transformer building - concrete repair work |
C03. Fuel oil pump station - pile cap preparation |
C05. Crusher house - 1st floor concrete slab |
C40. Light fuel oil storage retention work |
C71. Electrical building near Crusher house |
C72. Electrical building near Bunker bay area |
D01. Ash storage foundation rebar installation |
E05. Cooling water piping sleeper foundation piling extension |
E50 Cooling water culvert - sheet piling |
F06. Cable way foundation |
G05. Demineralized water production equipment erection |
G06. Demineralized water effluents foundation work |
G17. Auxiliary boiler foundation work |
G18. Reserve feed water storage foundation - rebar installation |
G25. Operational industrial water pump station foundation work |
G28. Oil & fire fighting water recovery pit - sheet piling |
L05. Absorber side wall rebar installation |
L05. Aeriation basin foundation work |
No comments:
Post a Comment
Note: only a member of this blog may post a comment.