B01. Boiler steel Structure Tire 4 erection,
and Hot & Cool Duct erection
View from West
B01. Steel Structure Tier 4 & Duct erection
B06. Bunker bay steel structure &
Silo cone erection - Viewfrom South
B01. Steel Structure Tier 4 & Duct erection
B06. Bunker bay steel structure &
Silo cone erection - View from North
B06. Bunker Bay area steel structure &
Silo cone Erection, view from East
B02. Chimney Erection, vew from North
B07. Fabric Filter pile cap preparation,
view from East
B33. Unit Electrical Building. 1st floor
slab concrete reform work, view from South
B33. Unit Electrical Building. 1st floor
slab concrete reform work, view from East
B35. Boiler Electrical Building
B63. Turbian Hall civil work,
excavation in progress
B68. Transformer Building side
wall concreting work, view from North
C05. Crusher House Foundation work
D01. Ash storage, Pile cap preparation
G06. Demineralized water plant
foundation concrete reform work
L10. Booster Fan Pedestal
L13. Aeration Basine area sheet piling
and excavation
C71. Electrical building near Crusher house,
piller concrete work in progress
Coal Handling Transfer Tower TT16 Steel
structure erection in progress