Thursday, 28 November 2013

28.11.2013 - Aerial Photo graph on November




B33.Unit electrical building, B68. Main
Transformer building. B63. Turbine Hall civil work.
 B06 Bunker Bay area steel structure and
Silo duct erection. view from East

G02. Raw Water Storage, G07. Demineralized
water storage, G05. Demineralized water production,
G06 Demineralized water Effluents.

E05. Cooling water piping sleeper.

B01. Boiler Steel structure Tier 5 & 6
erectioon and Duction erection, B35. Boiler
electrical building first floor column erection,
B07. Fabric filter lean concrete work,
D01.Ash storage pile cap preparation,
view from west

B02. Chimney erection, C05. Crusher house,
C71. Electrical building near Crusher house,
L05 Abosrber foundation, view from West

F01. Switch yard,

C04. Coal Yard, Coal Handling
Transfer Tower Steel structure erection

Coal yard, stack reclaimer area

M07. Cooling water outfall culvert

E05. Cooling water pumpstation, and Intake

Laydown area

Laydown area

Laydown area