B01. Boiler Steel structure
Tier 5&6 and Duct erection veiw from south
B01. Steel structure erection view from East
B06. Bunkerbay Steel structure
and Silo duct erection view from East
B07. Fabric Filter pile cap preparation
B33. Unit Electrical Building 2nd floor
Transf. area, Side wall erection,
B33. Unit electrical building
2nd floor column erection, view from North
B33. Unit electrical building, view from south
B35. Boiler Electrical Building, view from south
B35. Boiler Electrical building,
and Auxiliary Transformer area, view from East
B63. Turbine area over bridge
B63. Turbine area civil work, view from South
B68. Transformer building,
2nd step side wall erection, view from East
C05. Crusher House,
Foundation concrete and rebar installation
C40. Light fuel Oil Storage area, civil work
C71. Electrical building near Crusher house
D01. Ash Storage pile cap preparation
F01. Switchyard area Gantry erection
G02. Raw water storage 1 foundation concrete
G02. Raw water storage 2
foundation, steel rebar installation
G05. Demineralized water production area
foundation concrete
G07. Demineralized water storage
G25. Operational industrial
water pump station foundation work
L05. Absorber shell foundation area
steel rebar installation
L10. Booster fan foundation and pedestal
L13. Aeration basine area sheet piling
E02. Pump house civil work