Friday, 17 January 2014

16.01.2014


B01. Boiler steel structure,
pressure parts & duct erection
General view from West

B01. Steel structure tier 6&7 and Duct erection
view from South

B06. Bunker bay area steel structure
and Silo duct erection, view from East

B01. Pressure parts assembly at site

B01. Boiler  area lifting equipment erection

B02. Chimney erection,
concrete pouring in progress



D01. Ash storage foundation work

B07. Fabric Filter area Steel structure erection

B33. Unit Electrical building,
2nd floor column erection

B33. Unit electrical building transformer area

B35. Boiler electrical building
and Auxiliary transformer area

B63. Turbine hall basement concrete work,
View from North


B68. Main transformer building

C05. Crusher house foundation column erection

C03. Fuel oil pump station

C71. Electrical building near crusher house

C72. Electrical building near bunker bay

E05. Cooling water piping sleeper foundation

G05.Demineralized water production 
Foundation and column erection


G06. Demineralized water effluent foundation

G18. Reserve feed water storage

G17. Auxiliary boiler foundation work


G25. Operation industrial water pump station
foundation work


L05. Absorber wall erection,
sheet piling for GRP pipe

L13. Aeration basin area 
sheet piling for GRP pipe


Coal yard - Stack reclaimer A area

Stack reclaimer B - rail installation

Coal handling Transfer tower TT16
Steel structure erection

TT17 - Steel structure erection

TT18 - Foundation work

TT19 - Foundation work

TT20. Steel structure erection

TT21 - Steel structure erection

TT22 - Foundation work

TT23 - Foundaiton

TT24 - Foundation

C08. Coal handling electrical building area