B01. Boiler pressure parts assembly at site
B01. Boiler steel structure Tier 6 & 7
and duct erection, South side
B07. Fabric filter steel structure and
B01. Steel structure & Pressure parts erection
B02. Chimney pouring concrete
B02 Chimney erection
B06. Bunker bay area silo duct & steel erection
B07. Fabric filter steel structure erection
B07. Fabric filter casing assembly at site
D01. Ash storage foundation work
B33. Unit electrical building
3rd floor slab concreting work
B33. Unit electrical building transformer area
B35. Electrical building
B35. Boiler electrical building transformer area
B63. Turbine hall basement
Strip 3a, 4a concrete pouring completed
B68. Main transformer building
concrete repair work
C03. Fuel oil pump station
foundation excavation
C30. Fuel oil unloading area
C40. Light fuel oil storage retention work
C72. Electrical building near Crusher house
C72. Electrical building near bunker bay
F06. Cable bay area
G05. Foundation
G05. Equipment at site
G06. Foundation rebar installation
G17. Auxiliary boiler foundation
G25. Foundation work
L05. Absorber shell concrete work
C05. Crusher house column erection
L13. Aeration basin area sheet piling for GRP pipe
L13. Aeration basin area pile cap preparation