Thursday, 2 January 2014

02.01.2014


B01. Boiler Pressure parts assembly at site

B01. Boiler steel structure erection Tier 6 & 7,
View from South

B01. Boiler steel structure erection ,
View from West


B01. Boiler Pressure parts item at site

B02. Chimeny erection

B06. Bunker bay area, civil work

B06. Bunker bay area Silo Duct erection


B07. Fabric filter area foundation concrete,
North and South

B07. Fibric filter Steel structure assembly

B33. Unit electrical building, Transformer area
Foundation and side wall rebar installation, &
Emergency diesel generator foundation concrete


B35. Boiler electrical building 2nd floor Slab
concrete work

B35. Boiler electrical building
Auxiliary Transformer roof concrete

B63. Turbine hall 2A Strip concrete



B68. Main Transformer building

C05. Crusher house ground floor column erection

C30.  Fuel oil unloading area sheet piling

C40. Light fuel oil storage area retention work


C72. Electrical building Bunker bay area
Ground floor column erection

C71. Electrcial building Crusher house area
1st floor column erection


D01. Ash Storage pile cap preparation

E02. Cooling water piping sleeper foundation



G05. Demineralized water production area
column erection

G06. Demineralized water effluents
pile cap preparation

G17. Auxiliary boiler founation area leanconrete

G25. Operational industrial water pump station


L05. Absorber shell side wall rebar installation and
GRP under ground pipe sheet piling


C08. Coal Handling electrical building
foundation work

Stack reclaimer A area

Stack reclaimer B area

TT16 - Coal handling Transfer tower
steel structure erection 

TT17 - Coal handling Transfer tower
steel structure erection 


TT18 - Coal handling Transfer tower
foundation work  

TT19 - Coal handling Transfer tower
foundation work  

TT20 - Coal handling Transfer tower
steel structure erection  

TT21 - Coal handling Transfer tower
steel structure erection  

TT22 - Coal handling Transfer tower
foundation work  

TT23 - Coal handling Transfer tower
foundation work  

TT24 - Coal handling Transfer tower
foundation work  

E02. Cooling water pump station area flooding water
due to leakage or excavation 
                                   