Thursday, 24 October 2013

24.10.2013



B01. Boiler steel structure and Duct erection
General veiw From East

                                             B06. Bunker Bay area Steel Structure Tier #4
                                             erection, Cool Air duct & Silo Cone erection
                                             View from East
 B01. Boiler steel structure &
Hot air duct erection
 View from North


                                        B01/B06. Boiler steet structure Tire #4 erection,
                                        Hot & Cool Air Duct and Silo Cone erection
                                        view from South 

Bunker bay area Steel structure,
 Grating & Silo cone erection




B02. Chimney - concrete pouring on 
Windshield slide
 Started on 18-Oct-13



                                             B07. Fabric Filter pile replacing in progress

                                           
                                             B68. Transformer building -
                                             side wall concrete in progress

                                             B33. Unit Electrical building,
                                             First roof slab concrete work


B35. Boiler Electrical building,
ground floor roof slab work


B35. Boiler Electrical building -
Auxiliary Transformer foundation 
on 22-Oct-13


B35. Boiler Electrical building -
Auxiliary Transformer foundation - back filling
on 24-Oct-13

B63. Turbine Hall Civil work



                                             C05. Crusher house foundation - Rebar installation

                                             C07. TT23.  Transfer Tower foundation
                                                                   rebar installation

C40.  Light fuel oil storage foundation

L13. Aeration Basin area -Sheet piling

C71. Electrical building near Crusher House

D01. Ash Storage - pile cap preparation

F01. Switchyard Ganty erection
                                               
                                             L05. Absorber shell foundation, rebar installation

L10. Booster Fan Pedestal - steel rebar installation

Monday, 21 October 2013

22.10.2013



B01. Boiler Steel Structure Duct erection
view from North
                                             B01. Boiler steel structure Tier 4 erection, and
                                                      Silo Erection, view from South

                                             
                                             B01. Boiler Hot air Duct, Silo Cone erection



                                              B01. Boiler steel structure erection,
                                                      general view from West

                                              
                                             B02. Chimeny concreting first ring

B33. Unit Electrical Building

Friday, 18 October 2013

18.10.2013

B01. Boiler Steel structure & duct erection
Tier 3 & 4 in progress, view from North

                                                               B06/B01. Bunker bay Steel
                                                                strructure & duct erection
                                                                View from North               




                                                                Grating install in walkway
B06/B01. Bunker bay and Boiler area
Steel structure Tier 3&4 and  Duct erection, view from East

B06. Bunker bay are Tier 4 steel erection

B01. Tier 4 Steel structure
erection south side


                                             B01. Boiler area Duct erection, view from south     

                                              B01. Boiler Steel structure Tier 4 Erection,
                                                              view from West


                                              B02. Chimeny Slip form ring erection, over view

                                              B02. Chimeny Slip form ring erection, inside view



  
                                             C05. Crusher house foundation, rebar installation

                                             L10. Booster Fan foundation concrete
                                             
                                               
                                             B17. Boiler Flue Gas Duct foundation
                                              B33. Unit Electrical building concrete work,
                                              view from East

  
                                             B33. Unit Electrical building concrete work,
                                                       view from South

                                            B33. Unit Electrical building concrete work,
                                                      view from North
                                              B33. Unit electrical building ground floor

                                             B35. Boiler Electrical building, ground floor roof
                                                     concrete. view from West


                                             B35. Electrilcal building -
                                                     Auxiliry Transformer foundation


                                             B63. Turbine hall civil work





                                             B.68. Transformer building side wall concrete work 


                                              C40. Light Fuel Oil Storage Foundation
                                             C71. Electrical building near Crusher house,
                                                       Steel rebar installation

                                              D01. Ash Storage - pile cap preparation    

                                             L05. Absorber Foundation backfilling




                                             B07. Fabric filter piles replacing