Friday 31 January 2014

30.01.2014 - Aerial Photo graph as of 30 Jan 2014


Aerial Photo graph - January 2014
Power Block General view from East.

B33. Unit Electrical building, B63. Turbine hall,
B68. Main transformer building,
B06. Bunker bay steel structure and duct erection
View from East


Power Block East side,
G02 Raw Water Storage (2 Tanks),
G07 Demineralized water storage
G05. Deminerlized water production,
G06 Demineralized water effluents
G20. Potable water storage,
G25. Operational Industrial water pump station 

Power Block West Side
B01. Boiler Steel structure, Ducts &
 pressure parts erection, D01. Ash storage,
B07. Fabric filter steel structure erection
B10 ID fan Foundation,
C40. Light fuel oil retention work 
L10 Booster fan foundation
B35. Electrical building, L13 Aeration basine

Power block West side
C05. Crusher house,
C71. Electrical build near crusher house
B07. Hopper and Assembly erection
L05. Absorber shell erection
and sheet piling for GRP pipe, L24.
FGD duct foundation


BC -22 Conveyor foundation

Coal yard South side
Stack reclaimer foundation A&B


E50. Cooling water Outfal and Culvert
TT16/ TT17. Steel Structure erection
C73. Electrical building

Coal yard North side
TT20 & TT21 Transfer tower
steel structure erection

F01. Switch yard Gantry and support erection

E05. Cooling water pipe sleeper foundation

E02. Cooling water pump station and Intake

Material laydown area

Material laydown area

New - Material laydown area

New - Material laydown area

Wednesday 29 January 2014

29.01.2014



B01. Boiler pressure parts assembly at site


B01. Boiler steel structure Tier 6 & 7
and duct erection, South side

B07. Fabric filter steel structure and
B01. Steel structure & Pressure parts erection


B02. Chimney pouring concrete

B02 Chimney erection

B06. Bunker bay area silo duct & steel erection

B07. Fabric filter steel structure erection


B07. Fabric filter casing assembly at site

D01. Ash storage foundation work

B33. Unit electrical building
3rd floor slab concreting work


B33. Unit electrical building transformer area

B35. Electrical building

B35. Boiler electrical building transformer area

B63. Turbine hall basement 
Strip 3a, 4a concrete pouring completed




B68. Main transformer building
concrete repair work

C03. Fuel oil pump station
foundation excavation

C30. Fuel oil unloading area

C40. Light fuel oil storage retention work

C72. Electrical building near Crusher house

C72. Electrical building near bunker bay

F06. Cable bay area


G05. Foundation

G05. Equipment at site

G06. Foundation rebar installation

G17. Auxiliary boiler foundation

G25. Foundation work

L05. Absorber shell concrete work

C05. Crusher house column erection

L13. Aeration basin area sheet piling for GRP pipe

L13. Aeration basin area pile cap preparation