Thursday 28 November 2013

28.11.2013 - Aerial Photo graph on November




B33.Unit electrical building, B68. Main
Transformer building. B63. Turbine Hall civil work.
 B06 Bunker Bay area steel structure and
Silo duct erection. view from East

G02. Raw Water Storage, G07. Demineralized
water storage, G05. Demineralized water production,
G06 Demineralized water Effluents.

E05. Cooling water piping sleeper.

B01. Boiler Steel structure Tier 5 & 6
erectioon and Duction erection, B35. Boiler
electrical building first floor column erection,
B07. Fabric filter lean concrete work,
D01.Ash storage pile cap preparation,
view from west

B02. Chimney erection, C05. Crusher house,
C71. Electrical building near Crusher house,
L05 Abosrber foundation, view from West

F01. Switch yard,

C04. Coal Yard, Coal Handling
Transfer Tower Steel structure erection

Coal yard, stack reclaimer area

M07. Cooling water outfall culvert

E05. Cooling water pumpstation, and Intake

Laydown area

Laydown area

Laydown area

Wednesday 27 November 2013

27.11.2013





B01. Boiler Steel structure
Tier 5 & 6 erection, view from West

B06. Bunker bay area Steel structure
&  Silo duct erection, view from East

B07 Fabric Filter area Pile cap
and lean concrete work, view from East

B02. Chimney erection, view from bottom

B02. Chimney erection bottom area

B33. Unit Electric Building,
2nd floor column erection, 1st floor plastering

B35. Boiler Electrical building, view from North

B63. Turbine hall,
view from North side




B63. Turbine  - rebar installation
& concrete reform work,
view from South Side



C05. Crusher house foundation work

C71. Electrical building near Crusher house
C72. Electrical building near bunker bay

Crane - Assembly - 1200 Ton



D01. Ash storage, pile cap preparation

L05. Absorber foundation slab concrete

L13. Aeration Basement Sheet piling

Monday 25 November 2013

25.11.2013


B01. Boiler steel structure
Tier 5 & 6 and duct erection, view from South


B06. Bunker bay steel structure &
Silo duct erection, view from East

B01. Boiler Steel structure
Tier 6 & duct erection, view from south

B01. Boiler Steel structure erection,
view from West

B02. Chimney erection, (39m)
B02. Chimney bottom area


B33. Unit Electrical building
Transf. area 2nd floor, Side wall concreting

B33. Unit electric building,
plastering work, view from North

B33. Unit Electric building,
2nd floor column erection work, view from West

B07. Fabric Filter pile cap work

B35. Boiler Electrical building -
Auxiliary Transformer building

B35. Boiler Electrical building
Ground floor & First floor work, view from West

B63. Turbine Building, excavation, view from North

B63. Turbine building,
soil removal, view, from North

B63. Turbine building - steel rebar installation,
view from South


B68. Transformer building area,
2nd step firewall erection, view from North

B68. Transformer building,
rebar installation for fire wall

C05. Crusher house foundation rebar installation

C71. Electrcial building near crusher house

C40. Light fuel storage tank, retention work

C72. Electrical building near bunker floor,
foundation work

G02. Raw Water Storage tank
concrete reform work, (2nd tank)

G06. Demineralized water effluents,
steel rebar installation

G25. Industrial water pump station,
lean concrete work 

L05. Foundation slab concrete

TT16. Coal handling
transfer tower Steel structure erection

TT17. Coal handling Transfer
Tower steel structure erection

TT18. Coal handling transfer Tower
Foundation work

TT19. Coal handling Transfer Tower foundation

TT20. Transfer Tower steel structure erection

TT21. Transfer Tower Steel structure erection