B01. Boiler all Girder lifted
B01. Boiler Steel structure & Duct erection
View from South
B01. Boiler Steel structure & Duct erection
View from North
B01. All Girder on position
B01. Pressure parts assembly at site
B02. Chimeny erection,
concrete pouring in progress
B06. Bunker area Grating installation
B06. Bunker Bay area steel structure,
grating and Silo duct erection
B01. Silo duct after preassembly
B07. Fabric filter area,
Pile cap and substructure erection
B33. Unit electrical building
plastering work, view from North
B33. Unit electrical building 1st floor
B33. Unit electrical building transformer area
B35. Boiler electrical building,
1st floor column erection
B35. Boiler electrical building
Auxiliary transformer area
B63. Turbine hall, basement steel rebar installation
B63. Turbine over view from B33.
B68. Main transformer building
C05. Crushere House foundation work
C40. Light fuel oil storage area retention work
C71. Electrical building near Crusher house
C72. Electrical building near bunker bay
D01. Ash storage pile cap &
lean concrete preparation
E05. Cooling water piping sleeper's foundation
G02. Raw water storage Foundation
G25. Operational water pump station foundation
L05. Absorber Tower side wall rebar installation
Coal handling Transfer Tower
Steel structure erection
TT16
TT17
TT18
TT19
TT20
TT21
TT22
TT23
C71. Electrical building near Crusher house
C72. Electrical building near bunker bay
C73. Electrical building south Coal Yard