| B01. Boiler Pressure parts assembly at site |
| B01. Boiler pressure parts item for lifting position |
| B01. Boiler pressure parts item preparation for lift |
| B01. Boiler pressure parts for lifting position |
| B01. Pressure parts lifting position |
| B06. Bunker bay area steel structure & silo duct erection, view from south |
| B01. Boiler steel structure, duct and pressure parts erection, view from South |
| B01. Boiler Steel structure rear side |
| B01. Boiler steel structure, preassure parts and duct erection, B07. Fabric filter steel structure & hopper erection, view from West |
| B01. Boiler steel structure, Duct & Preassure parts erection B07. Fabric filter hopper erection view from West |
| B07. Fabric filter hopper erection , view from North |
| B06. Bunker bay area steel structure and Silo Duct erection, and Chimeny, view from West |
| B06. Bunker bay area Mill foundation completion |
| B07. Fabric filter Hopper casing assembly (B17 area) |
| B07. Fabric filter steel structure and Hopper erection, view from South |
| B07. Fabric filter hopper erection, view from North |
| B17. Steel structure erection |
| B33. Boiler electrical building plastering work, view from North |
| B33. Unit electrical building ground floor- HVAC work |
| B33. Unit electrical building 1st floor completion of painting |
| B33. Unit electrical building transformer area |
| B33. Unit electrical building 3rd floor column erection |
| B33. Boiler Electrical building, plastering work, view from East |
| B35. Boiler electrical building Transformer area, view from North |
| B35. Boiler electrical building ground floor, painting and HVAC work |
| B35. Boiler electrical building 1st floor painting and HVAC work |
| B63. Turbine hall West side |
| B63. Turbine hall view, North |
| B63. Turbine hall pedestal concrete work, view from North |
| B68. Main transformer building concrete repair work |
| B68. Auxiliary transformer building |
| B68. Main transformer building ,view from East |
| C03. Fuel oil pump station foundation work |
| C05. Crusher house 1st floor column erection |
| C30. Fuel oil unloading area |
| C40. Light fuel oil storage retention work |
| C71. Electrical building near Crusher house |
| C72. Electrical building near Bunker bay area |
| D01. Ash storage foundation concrete |
| E05. Cooling water piping sleeper fooundation piling extension |
| F06. Cable way foundation |
| G05, Demineralized water production equipment erection |
| G05. Equipment erection |
| G06. Demineralized water effluent foundation |
| G10. Emergency diesel generator foundation |
| G16. Industrial waste water treatment |
| G17. Auxiliary Boiler foundation work |
| G18. Reserve feed water storage |
| G25. Operational industrial water pump station foundation work |
| G25. Operation industrial water pump station foundation and column erection, view from South |
| L05. Absorber shell wall concrete work |
| L13. Aeration basine foundation work |
| L13. Aeration basin foundation work |
| L24. FGD Duct foundation work |
No comments:
Post a Comment
Note: only a member of this blog may post a comment.