B01. Pressure parts errection, view bottom |
B01. Boiler pressure parts erection, view from bottom |
B01. Pressure parts header lifting position |
B01. Piping erection |
B01. Boiler pressure parts header liftiing |
B01. Pressure parts assembly at stie |
B01. Boiler steel structure, duct, Pressure parts & Silo duct erection |
B01. Boiler steel structure erection view from South |
B01. Boiler steel structure and B07. Fabric filter steel structure erection |
B01. steel structure and B07. Hopper erection, view from West |
B06. Bunker bay area steel structure and Silo duct erection |
B06. Bunker bay area Mills foundation concrete |
B07. Fabric filter steel structure and hoppeer erection , view from East |
B17. Flue gas Duct foundation- hopper casing asembly |
B17. Flue gas duct foundation area - Hopper casing assembly
|
B07. Fabric filter steel structure and Hopper erection |
B33. Unit electrical building ground floor - HVAC Duct frame installation |
B33. Unit electrical building 1st floor plastering and painting work |
B33. Unit electrical building Transformer area |
B33. Unit electrical building 3rd floor slab concrete, view from East |
B33. Unit electrical building view from South |
B35. Boiler electrical building, 1st floor HVAC work and Plastering and painting work |
B35. Boiler electrical building, plastering work |
B35. Boiler electrical building, ground floor HVAC work, Plastering and painting work |
B35. Boiler electrical building Auxiliary transformer area |
B63. Turbine hall, view from North |
B63. Turbine hall side wall concrete - view from North |
B63. Turbine hall pedestal, view from North |
C03. Fuel oil pump station foundation work |
C05. Crusher house |
C71. Electrical building near crusher house |
C72. Electrical buildding near Bunker bay |
E05. Cooling water piping sleeper foundation, piling extension |
D01. Ash storage foundation |
E50. cooling water culvert turbine hall to Aeration basin |
F06. Cable Way foundation |
G06. Demineralized water effluent |
G10. Emergency diesel generator foundation |
G16. Industrial waste water treatment plant |
G18. Reserve feed water storage |
Operational Industrial water pump station |
G28. oIL & Fire Fighting water recovery pit |
L05. Absorber shell concreting work |
L13. Aeration basine |
L24. FGD Duct foundation work |
B68. Main transformer building Concrete repair work |