B01. Boiler steels erection, view from North |
|
B01. Boiler pressure parts assembly at site. |
|
B01. Boiler steel structure and duct erection,
view from South |
|
B01. Boiler steel structure, Duct and
pressure parts erection, view from South |
|
B01. Boiler steel structure at rear side |
|
B01. Boiler steel and pressure parts erection,
B07. Fabric filter hopper erection, view from West |
|
B01. Boiler steel and pressure parts erection,
B07. Fabric filter hopper erection, view from West |
|
B01. Boiler steel structure and
B02. Fabric filter hopper erection, general view from West |
|
B01. Boiler pressure parts item lifting position fit up |
|
B06. Bunker bay area mill foundation complete
and start erection activity |
|
B06. Bunker bay area steel structure and Silo duct erection
|
|
B07. Fabric filter steel structure and hopper erection, view from
North |
|
B07. Fabric filter hopper erection view from South |
|
B01. G17 Auxiliary boiler foundation &
C40. Light fuel oil storage retention work |
|
B17. Flue gas duct assembly and steel structure erection |
|
B17. Flue gas duct steel structure erection |
|
B33. Unit electrical building ground floor HVAC erection |
|
B33. Unit electrical building 1st floor HVAC erection work |
|
B33. Unit electrical building 3rd floor column erection,
view from East |
|
B33. Unit electrical building general view from South |
|
B35. Boiler electrical building plastering and painting,
view from East |
|
B35. Boiler electrical building groud floor painting |
|
B35. Boiler electrical building 1st floor HVAC work |
|
B35. Boiler electrical building transformer building area,
view from West |
|
B63. Turbine hall west side wall, view from North |
|
B63. Turbine hall side wall, view from North |
|
B63. Turbine hall wall concrete South end |
|
B63. Turbine hall side concrete wall - west side,
view from South |
|
B63. Turbine hall concrete pedestal, view from North |
|
B63. Turbine hall rebar install for concrete slab 0 level
view from North |
|
B63. Turbine hall rebar installation for slab concrete |
|
B68. Auxiliary transformer building side rebar installation |
|
B68. Main transformer building |
|
B68. Main transformer building |
|
C03. Fuel Oil Pump station foundation work |
|
C05. Crusher House 1st floor column erection |
|
C30. Fuel oil unloading area foundation work |
|
C40. Light fuel oil storage retention work |
|
C72. Electrical building near Crusher house |
|
C72. Electrical building near Bunker bay area |
|
D01.Ash storage structure erection |
|
E05. Cooling water piping sleeper foundation work |
|
E50. Cooling water culvert foundation
Turbine hall to Aeration Basin |
|
F06. Cable way foundation
Main transformer building to Switchyard |
|
G05. Demineralized water production equipment erection |
G25. Operational industrial water pump station foundation
and column erection, view from North |
|
G06. Demineralized water effluent |
|
G16. Industrial waste water treatment area |
|
G25. Operation Industrial water pump station column
erection, view from South |
|
G18. Reserve feedwater storage |
|
G28. Oil & Fire fighting water recover pit |
|
L05. Absorber shell side wall rebar installation |
|
L13. Aeration basin foundation and side wall concrete work |
|
L24. FGD Duct foundation work |