| Power general view from North |
| Boiler area PA & FD fan erection |
| Fabric filter area |
| FD Fand and Duct erection - North side |
| Scrape Collecting system conveyor erection |
| Scrape collecting system conveyor erection view from South |
| B89B Gas storage foundation |
| Main cooling water outlete piping |
| Steam blow out pipe erection |
| Main cooling water piping - backfilled |
| Turbine hall general view from North |
| G02 - Tank erection finishing work |
| G07 - Tank erection |
| Turbine hall generqal view from East |
| Turbine hall East side - Main cooling water piping back filled |
| Cable pulling- Unit electrical building area |
| Vessels Insulation and cladding work |
| Vessels insulation and cladding work |
| Turbine hall |
| Turbine hall |
| Turbine hall |
| Turbine hall |
| Turbine hall |
| Turbine hall |
| Turbine hall |
| Turbine hall |
| Turbine hall |
| Turbine hall |
| Turbine hall |
| Turbine hall |
| Turbine hall |
| Waste water treatment area |
| FGD pumpstation and Aeration basine |
| Auxiliar boiler building and Lfo area |
| Acid pond |
| Water treatment area |
| Aeration basine |
| Industrial water pump station |
| Auxiliary building |
| PA and FD fan and duct erection - South side |
| Fabric filter area - insualtion work - South side |
| Waste water treatment equipment erection |
| FGD pumpstation area |
| FGD pumpstation |
| Aeration basin |
| FGD area |
| Boiler area general view from South |
| FGD area |
| Absorber area |
| GGH Rotor at site |
| GGH heavy equipment at site |
| ASH handling system - erection |
| Air compressor build electrical work |
| FGD Duct insulation and cladding work |
| Boiler area - General view from North |