Overall Plant
Progress photo
Power plant general view from North 

Power plant general view from North

Fabric filter area - North

Boiler North side

Boiler FD&PA fan area - North

Slag Conveyer sys work

89C gas storage area

Turbine Hall - North side

Auxiliary transformer area


Main Trannsformer area

Demin tank area

Raw water storage tank area

Turbine hall view from East

Exhaust Tank area

HP Heater tank insulation 11m level

HP Heater tank insulation 16m level

Turbine hall

Turbine hall

Turbine hall

Water pit civil work

Acid pit area civil work

Industrial water pump station

Turbine hall South side

Boiler area - South side

Waste water treatment area

Waste water treatment area equipment erection

Waste water treatment area


FGD Pump station
 
Fabric filter area - South side

Aeration station

FGD area

Absorber area - West side

Ash handling system erection

Ash handling system & Fabric filter area

Air Ash compresor building