Power Block General view from East
B63. Turbine Hall, B33. Unit Electrical Building
B68. Transformer foundation - View from East
E05. Cooling water piping sleeper
B01. Boiler Duct Assembling area
Power Block General view from West
B02. Chimeny Slip form erection, B17. Flue Gas duct foundation concrete, L05. Abasorber foundation.
B10. ID Fan North foundation, L10. Booster Fan
foundation B35. Boiler Electrical Building
L13. Areation Basin Piling work
F01. Switchyard - General view from East
E02. Cooling water pumphouse
C04. Coal Yard view from North,
Coal Yard 6th stage Sand filling in progress, Subcontractor site office & laydown area
Coal Yard South side, Stacker/Reclaimer foundation
work in progress