Tuesday 14 January 2014

14.01.2014


B01. Boiler pressure parts assembly at site

L13. Aeration Basin and
Under ground GRP piping sheet piling

L05. Absorber Side wall reform work and
Under ground GRP pipe sheet piling


G25. Operational industrial water pump station


G10. Emergency Diesel Generator foundation

G17. Auxiliary Boiler foundation work

G06. Demineralized water effluents

E05. Cooling water piping sleeper foundation

C72. Electric building near bunker bay

D01. Ash storage foundation work

C71. Electrical building
near crusher house 2nd floor Slab concrete

C05. Crusher house foundation
and column erection

C40. Light fuel oil storage retention work

B68. Main transfor building plastering work


B63. Turbine  hall
basement rebar installation on North side




B35. Boiler electrical building
auxiliary transformer area

B33. Unit electrical building, view from East

B33. Unit electrical building
1st floor plastering work

B07. Fabric filter steel structure erection,
view from West

B07. Fabric filter steel structure erection,
view from South

B06. Bunker bay area steel structure,
piping  and silo duct erection. view from East

B01. Boiler steel structure area
lifting equipment erection, view from West

B01. Boiler Steel structure erection,
view from South

No comments:

Post a Comment

Note: only a member of this blog may post a comment.