Saturday 13 June 2015

13.06.2015

Boiler SSC north side
Boiler SSC north side
MCW outlet header piping at Turbine hall
MCW outlet header piping at Turbine hall
MCW outlet header piping at Turbine hall
MCW outlet header piping at Turbine hall
Steam blow piping at Turbine hall
Steam blow piping at Turbine hall
Cooling water piping at Turbine hall backfilled
Cooling water piping at Turbine hall
Cooling water piping at Turbine hall
Cooling water piping at Turbine hall backfilled
Turbine hall at Level +16.0m
Turbine hall at Level +16.0m
Turbine hall at Level +16.0m
Turbine hall condenser neck welding
Turbine hall Lube oil room