17.07.13


B06. Bunker Bay foundation South Side
Applying water proof painting

                                        B06. Bunker Bay Stengthning work - North side
                                                   steel fixing for concrete       

B06. Bunker Bay North side - Rebar installation 

                               B01. Boiler Foundation concection beam concrete-
                                       Backfilling, view from North side 

                                B01. Boiler Foundation concection beam concrete-
                                        Backfilling, view from South side 

                                 B01. Boiler Foundation connection beam,
                                 strengthning work - View from North side


                                B01. Boiler Foundation connection beam,
                                strengthning work - View from South side

                              
                                  B01. Boiler FD Fan Rebar installation work 

                                 B63. Turbain Hall North side. Bore piling work 

B63. Turbain Hall North side. Bore piling 

B63. Turbain Hall. South side piling work

B63. Turbain Hall. East Side, view from South

                                       B33. Boiler Electrical Building,
                                       Ground floor reinforcement work

                                       B02. Chimney. Foundation back filling

                              L10. Booster Fan Foundation reinforcement work

                                B94. Air Preheaters Washing Basin
                                        Pile cap preparation

                                 B17 - Flue Gas duct foundation
                                          reinforcement work

D01 - Ash Storage - Bore piling work 

                                 L05 - FGD Absorber - Pile cap preparation


                                    C40. Light Fuel Oil Storage - Piling work 
                                      
 
                                  Boiler Duct preassembling - Inside the plant


                                     Ash Silo - Preassembly in side the plant


F01 - Switchyard 2ASlab Work 


F01. Switchyard 3A Slab reinforcement work

C04 - Coal Yard Soil filling - view from North

Tuesday, 16 July 2013

16.07.13

B01.Bunker Bay foundation South Side
Applying water proof painting

                                         B01. Bunker Bay Strengthning work - South side 

B01. Bunker Bay Strengthning work - North side
Steel fixing for concrete

B01 - Bunker Bay North side - 
Rebar installation started


                                                        B01 - Boiler foundation Pedestal
                                                            backing filling F8 & F10


                                          B01- Boiler Foundation Connection Beam
                                                            strenghtning work 


                                               B01. Boiler Foundation Connection Beam
                                                strengthning work  - Vew from North side

                                         B01. Boiler Foundation Connection Beam Concrete -
                                                            View from North side     

B01 - Boiler foundation Backing filling
 Pedestal F8&10

B01. Boiler FD Fan Rebar installation work

                                          B35.  Boiler Electrical Building foundation work.


                                                    B94. Air preheaters washing Basin
                                                                     Piling work








                                          B01. Boiler foundation Connection Beam &
                                                          PA Fan foundation


                                                   B63. Turbain Hall Foundation work -
                                                   Bore piling work, view from North          
 

                       
                                          B33. Boiler Electrical Building ground floor work
                                                                   view from East


                                         B68. Transformer Foundation concrete

                                     
                                         C06 - Coal Conveyor between C05 & C07 (TT23)


                                          B02 - Chimeny - Foundation Finishing work

                                         B17 - Flue Gas Duct Foundation work - Steel fixing
 

                                         L05 - FGD Absorber - Pile Cap preparation


                                            C40. Light Fuel Oil Storage - Piling work


                                       B63. Turbain Hall Foundation work - View from north

                                         B63. Turbain Hall - East side piling work

                                                B63. Turbain Hall - North side, Bore piling



                                          B63. Turbain Hall- view from South, Piling work



Saturday, 13 July 2013

13.07.13

13.07.13 Safety tool talking

                                                      E05 - Cooling water piping sleeper


                                                E02 - Cooling water pumphouse

                                                 B01 - Boiler Pedestal Concreting           


                                              B01 - Boiler remedial strengthning work

                                                  Boiler Duct pre-assambling  in side plant
 
                                                                C40 - Piling work      

Friday, 12 July 2013

12.07.13


 B01 - Boiler Cavity - Looking North_1_s

B01 - Boiler Cavity - Looking North 2_s

Switchyard - Warehouse Looking North  
  
  
Switchyard - Warehouse - looking_west_1


 Switchyard - Warehouse - Looking_west_2