Monday 28 April 2014

29.04.2014

ADV Module assembly

B01. Rear Side Steel structure erection

B01. Boiler pressure parts erection, view from North

B01. Pressure parts erection, view from North

B01. Pressure parts erection, view from Bottom

B01. Boiler steel structure erection , veiw from East

B01. Boiler steel structure & duct erection,
View from South


B01. Boiler steel strcture & Pressure parts erection,
B07. Fabric filter casing erection
View from West

B06. Bunker bay area sole plate installation

B06. Bunker bay area sole plate installation

B07. Fabric filter hopper casing erection, view from North

B17. Flue gas duct assembly and erection,
and steel structure erection

B33. Unit electrical building ground floor cable tray installation

B33. Unit electrical building transformer area, view from East

B33. Unit electrical building view from South

B35. Boiler electrical building, veiw from East, painting

B35. Boiler electrical building, ground floor cable tray erection

B35. Boiler electrical building First floor HVAC Duct work,
and flooring

B63. Turbine hall, Ground floor slab concrete & Piller work
View from West

B63. Turbine hall  ground floor slab rebar installation

B63. Turbine hall South side rebar installation


B06. Bunker bay mill area sole plate installation

B63. Turbine hall viewfrom North

B63. Turbine hall steel structure erection, view from North

B68. Auxiliary Transformer side concrete and bore piling

b68. Main transformer building plastering and grating work

B63. Turbine hall steel structure erection, view from East

C72. Electrical building near bunker bay area

D01. Ash storage structure concrete pouring

E05. Cooling water piping sleeper foundation work


E05. Demin. water proudction equipment erection

G08. Compressed air production
Foundation and column ereciton

G25. Operational Industrial water pump station
Steel structure erection

G25. Operational industrial water pump station
Building side plastering work

L13. Aeration station basement slab concrete work 

L13. Aeration station piling work

L13. Aeration basin slab concrete work

No comments:

Post a Comment

Note: only a member of this blog may post a comment.