Thursday 12 June 2014

12.Jun.2014


B01. Boiler pressure parts erection, view from bottom


B01. Boiler pressure parts erection,
view from bottom



B01. Boiler steel structure, view from North



B01. Boiler steel structure & Silo duct erection,
B63. Turbine hall steel structure erection
view from East



B01. Boiler steel structure and pressure parts erection
B07. Fabric filter casing erection
General view from West

B06. Pulverizer erection

B06. Bunker bay area Silo duct and Steel structure roof ereciton

B07. Fabric filter casing erection

B07. Fabric filter casing erection

B17. Flue gas duct and steel structure erection

B17. Flue gas duct steel structure erection


B33. Unit electrical building ground floor cable tray erection

B33. Unit electrical building 1st floor

B33. Unit electrical building view from East

B33. Unit electrical building view from South

B35. Boiler electrical building, view from East

B35. Boiler electrical building ground floor Cable tray erection

B35. Boiler electrical building 1st floor


B63. Turbine hall view from North

B63. Turbine hall piller erection




B63, Turbine hall view from North
North side steel rebar installation for concrete


B63. Turbine steel structure erection -Overall view


B63. Turbine Hall steel structure erection -
South side ( overall view )

B63. Turbine hall steel structure erection, view from South


B63. Turbine hall - Feed water pump at site

B63. Feed water pump at site

B63. Turbine hall, Dosing system




B68. Main transformer

B68. Auxiliary transformer building

C03_40 Fuel oil pump station foundation

C05. Crusher house building

C40. Light fuel oil storage area


C72. Electrical building near crusher house
 7
C72. Electrical building near Bunker bay

D01. Ash storage structure erection

E05. Cooling water under ground piping installation

E50. Cooling water Outfall culvert foundation,
Turbine hall to Aeration Station

F06. Cable way foundation


G05. Demin water production equipment erection


G05. Demin plant steel structure erection

G07 and G20 Tank erection

G08. Compressed air production building
and H03. Cable tray racket foundation

G17. Auxiliary boiler foundation

G25. Operation industrial water pump station



G28. Oil & Fire water recover pit

G28. - Overall view


H03. Pipe rack foundation - near tank area

H03. Pipe rack foundation - near tank area

L05. Absorber shell concrete work

L13. Aeratin basin

L24. FGD duct foundation