Sunday 21 September 2014

21.09.2014 - Power Block



Power Block general view from North

B01. Boiler Hot and cool air duct

B01. Boiler erection



B01. Boiler, duct & pressure parts erection, view from bottom

Air pre heater erection

B01. Piping erection

B63. Turbine hall large bore pipe erection

B01. Boiler panel pressembly

B06. Bunker bay area pulverizer erection

B06. Bunker bay area, pulverizer erection, view from South

B06. Fabric filter casing erection

B17. Flue gas duct and  steel structure erection


B17. Flue gas duct erection


B33. Unit electrical builind cable pulling

B33. Cable pulling




B33. Unit electrical building 1st floor LV switchgear panel installation



2nd floor Panel erection

B33. 3rd floor - control room area civil work

B33. Cable pulling


B33. Unit electrical building, plastering and painting, view from South

B35. Boiler electrical building, Auxiliary transformer

B35. Boiler electrical  building cable pulling


B63. Turbine hall Cooling water outlet pipe walve erection

B63. Turbine hall general view from North
Civil and mechanical erection


B63. Turbine hall, general veiw from North
Civil and mechanical erection


B63. Turbine hall main cooling water inlet pipe ereciton

B63. Main feed water pump alignment

B63. Turbine hall condenser neck erection

B63. Turbine hall -5.2 m level civil work

B63. Turbine hall 16 m lvl

B63. Turbine hall 16 m level, Turbine table and heater

B63. Turbine hall general view from South


B01. Boiler duct & steel erection


B68. Main transformer erection



B68. Auxilary transformer erection


C03 Fuel oil pumpstation civil work

C05. Crusher house

C40. Fuel oil tank erection

C72. Electrical building and tower

D01. Ash stroage tank structure

E05. Coooling water under ground pipe erection

E50. Outfall culvert - turbine hall to Aeration base

F06. Cable bay found

G02.  Raw water supply storage tank erection

G05. Demin plant steel structure erection
G07. Tank erection


G05. Demin plant equipment erection

G07. Demin tank erection

G28. Recovery pit concrete rebar installation


G08. Compressed air building




G17 Auxiliary boiler erection


G20. potable tank erection

G25. Water pump station bulding, and G02 tank erection

G28. concrete rebar installation


L05. Absorber shell & GRP flange arranging



H03. Pipe rack

No comments:

Post a Comment

Note: only a member of this blog may post a comment.