Monday 9 September 2013

09.09.2013

B01. Boiler steel structure erection,
view from Southeast


B06. Boiler Bunker Bay steel structure erection,
view from North


B01. Boiler steel structure erection,
view from South



B01. Boiler steel structure erection,
view from West


B02. Chimney Slip ring form erection


B10. ID Fans South foundation rebar work,
view from west


B17. Flue Gas Duct backfilling completed


B33. Unit Electrical Building groundfloor civil work


B35. Boiler Electrical Building foundation,
rebar & formwork


B63. Turbine Hall civil works



B68. Transformer foundation area


C05. Coal Crusher House pile cap preparation work


C07 - TT24 Transfer Tower foundation,
backfilling work


E09. MCW Discharge Channel civil works



F01. Switchyard foundation, rebar work


F01. Switchyard Gantry erection


G05. Demin Water Production foundation, formwork


G06. Demin Water Effluents foundation, formwork


G07. Demin Water Storage tank foundation,
rebar work


L05. FGD Absorber pile cap preparation


L10. Booster fans foundation, formwork removal


L13. Aeration Basin pile cap preparation


L24. FGD Duct pile cap preparation